Risk register template for Excel and Jira (CSV)
A free risk register template with 15 sample IT project risks, as a CSV that opens in Excel, and the steps to import it into Jira with the right fields.
A risk register template is a spreadsheet with one row per risk and a column for everything you need to manage it. The one below is a CSV file that opens in Excel, with 15 realistic risks from an IT project already filled in and every column explained. The second half of this guide moves it into Jira, where each risk becomes a work item with an owner, a rating and a review date.
Download the template
Download risk-register-template.csv
The file has 16 columns and 15 risks from a project that moves an online store to a new e-commerce platform. Double-click it to open it in Excel. If every row lands in a single column, your Excel uses a different list separator: import the file from Excel’s Data tab instead (From Text/CSV on Windows) and choose comma as the delimiter. Save a copy as .xlsx while you edit, so formulas and formatting survive.
The columns, explained
| Column | What goes in it | Example (R01) |
|---|---|---|
| ID | A short reference for meetings and minutes | R01 |
| Summary | The risk in a few words | Payment provider API change breaks checkout |
| Description | What could happen, and the context | The payment provider is retiring the API version our checkout uses |
| Cause | What would make it happen | Our integration is pinned to the old API version |
| Consequence | What happens if it does | Customers can’t pay by card until a fix ships |
| Risk category | The kind of risk, for grouping and reports | Vendor |
| Owner | One person who watches the risk and acts on it | James Whitfield |
| Risk likelihood | How likely, from 1 Rare to 5 Almost certain | 3 Possible |
| Risk impact | How bad, from 1 Insignificant to 5 Severe | 4 Major |
| Risk score | Likelihood × impact, from 1 to 25 | 12 |
| Rating | The band the score falls in | High |
| Risk response | Avoid, Reduce, Transfer or Accept | Reduce |
| Response plan | The actions that carry out the response | Upgrade to the current API version; add a contract test |
| Next review | When the owner next checks the rating | 2025-11-20 |
| Status | Identified, Assessed, Treating, Monitoring or Closed | Treating |
| Work type | Risk, so the importer creates Risk work items | Risk |
The two scales, with a plain definition for each level:
| Level | Likelihood | Impact |
|---|---|---|
| 1 | Rare: only in exceptional circumstances | Insignificant: no noticeable effect on cost, dates or service |
| 2 | Unlikely: could happen, but isn’t expected | Minor: a small overrun the plan can absorb |
| 3 | Possible: might well happen during the project | Moderate: a visible slip or overrun, or a service problem customers notice |
| 4 | Likely: will probably happen | Major: a missed milestone, a large overrun, or an outage of a key service |
| 5 | Almost certain: expected to happen | Severe: the project misses its goal, or customers or regulators are affected |
The 15 sample risks
| ID | Risk | Category | Likelihood | Impact | Score | Rating | Response |
|---|---|---|---|---|---|---|---|
| R01 | Payment provider API change breaks checkout | Vendor | 3 | 4 | 12 | High | Reduce |
| R02 | Order history migration overruns the cutover window | Schedule | 4 | 4 | 16 | High | Reduce |
| R03 | Only one developer knows the tax calculation module | People | 2 | 4 | 8 | Medium | Reduce |
| R04 | Cloud hosting costs exceed the budget | Cost | 3 | 3 | 9 | Medium | Reduce |
| R05 | Customer data exposed through misconfigured storage | Security | 2 | 5 | 10 | High | Reduce |
| R06 | No tested rollback for the database migration | Technical | 4 | 5 | 20 | Extreme | Reduce |
| R07 | Go-live falls in the year-end trading peak | Schedule | 3 | 4 | 12 | High | Avoid |
| R08 | Layout faults in older browsers | Technical | 3 | 1 | 3 | Low | Accept |
| R09 | Late change requests from the marketing team | Schedule | 4 | 3 | 12 | High | Reduce |
| R10 | Critical vulnerability in an open-source library | Security | 3 | 3 | 9 | Medium | Reduce |
| R11 | Hosting region outage after launch | Operational | 1 | 5 | 5 | Medium | Accept |
| R12 | Implementation partner overruns its estimate | Cost | 3 | 3 | 9 | Medium | Transfer |
| R13 | Testers unavailable at quarter-end | People | 4 | 2 | 8 | Medium | Reduce |
| R14 | French translations arrive late | Schedule | 2 | 2 | 4 | Low | Accept |
| R15 | Old platform switched off before order records are archived | Compliance | 2 | 5 | 10 | High | Avoid |
Every response type appears: R07 and R15 avoid the risk by changing the plan, R12 transfers the overrun to the partner with a fixed price, and R08, R11 and R14 are accepted and watched.
The header row and the first risk, if you’d rather paste than download:
ID,Summary,Description,Cause,Consequence,Risk category,Owner,Risk likelihood,Risk impact,Risk score,Rating,Risk response,Response plan,Next review,Status,Work type
R01,"Payment provider API change breaks checkout","The payment provider is retiring the API version our checkout uses. If the change lands before we upgrade, card payments fail.","Our integration is pinned to the old API version.","Customers cannot pay by card until a fix ships.",Vendor,James Whitfield,3 Possible,4 Major,12,High,Reduce,"Upgrade to the current API version; add a contract test for the payment API to the build; subscribe to the provider changelog.",2025-11-20,Treating,Risk
Score and rating formulas for Excel
The score and rating in the file are plain values, ready to import. While you edit in Excel, two formulas keep them right. With Risk likelihood in column H and Risk impact in column I, put this in J2 for the score:
=LEFT(H2,1)*LEFT(I2,1)
And this in K2 for the rating:
=IF(J2>=20,"Extreme",IF(J2>=10,"High",IF(J2>=5,"Medium","Low")))
Fill both down the column. The bands are a common way to split the 1 to 25 range; your organization may set its own.
| Rating | Scores |
|---|---|
| Low | 1 to 4 |
| Medium | 5 to 9 |
| High | 10 to 16 |
| Extreme | 20 to 25 |
When you save as CSV again, Excel writes the results, not the formulas, which is what the importer needs.
Import the template into Jira
1. Create the work type and fields
A Jira admin creates a Risk work type under Settings > Work items > Work types, and these fields under Settings > Work items > Fields > Create new field, then adds the fields to the Risk work type’s screens. In a team-managed space, a space admin adds both under Space settings > Work types.
| Field | Type | Options, spelled exactly as in the file |
|---|---|---|
| Risk likelihood | Select List (single choice) | 1 Rare, 2 Unlikely, 3 Possible, 4 Likely, 5 Almost certain |
| Risk impact | Select List (single choice) | 1 Insignificant, 2 Minor, 3 Moderate, 4 Major, 5 Severe |
| Risk score | Number Field | None |
| Risk category | Select List (single choice) | Technical, Schedule, Cost, Security, Vendor, People, Compliance, Operational |
| Risk response | Select List (single choice) | Avoid, Reduce, Transfer, Accept |
| Cause, Consequence, Response plan | Paragraph | None |
| Next review | Date Picker | None |
In a team-managed space the same types are called Dropdown, Number, Date and Paragraph.
If Risk doesn’t appear as a work type when you create or import, it isn’t in the space’s work type scheme yet: add it to the scheme, as an Atlassian Community thread shows.
The file uses three statuses: Assessed, Treating and Monitoring. If your workflow’s statuses have other names, change the file, or leave Status out of the mapping and let every risk start in the workflow’s first status.
2. Prepare the file
- Owners. The importer matches people by email address or Atlassian account ID, not by name. It can also create accounts for people it doesn’t find, as active users who count toward your license, so replace each name in Owner with the email address of someone already on the site, or leave Owner out of the mapping.
- Select values. Spell every value in a select column exactly as its option, capitals and spaces included, or translate it with Map field value when you import.
- Dates. Next review is in yyyy-MM-dd. If you saved the file from Excel, look at the column first: Excel may write dates in your local format, such as 11/20/2025, and the importer has to be told which format to expect.
- Headers. Keep the header row as it is. The importer needs a Summary column, and punctuation in headers can confuse it.
3. Run the import
You need the Make bulk changes global permission and permission to create work items in the space. Jira admins can also use Settings > System > External System Import > CSV.
- Go to Filters > Search work items, then select More actions (•••) > Import work items from CSV.
- Choose the file, leave Use an existing configuration file cleared, and select Next.
- Choose the space and set the date format to match the file:
yyyy-MM-ddas downloaded, orM/d/yyyyfor dates like 11/20/2025. - Map the columns as in the table below. Select Map field value for any column whose values need translating to Jira’s.
- Select Validate, fix anything it reports, then select Begin import.
| CSV column | Jira field |
|---|---|
| ID | Leave unmapped, or map to a short text field such as Legacy ID if old minutes refer to R01 |
| Summary, Description | Summary, Description |
| Cause, Consequence, Response plan | The Paragraph fields with the same names |
| Risk category, Risk likelihood, Risk impact, Risk response | The select fields with the same names |
| Owner | Assignee |
| Risk score | Risk score |
| Rating | Leave unmapped: JQL on Risk score gives the same bands and can’t drift out of step |
| Next review | Next review |
| Status | Status, if the statuses exist |
| Work type | Work type |
4. Check the result with JQL
| Check | JQL | Expect |
|---|---|---|
| Everything arrived | project = RISK AND type = Risk AND created >= startOfDay() |
15 work items |
| No missing ratings | project = RISK AND type = Risk AND ("Risk likelihood" is EMPTY OR "Risk impact" is EMPTY) |
None |
| Dates came through | project = RISK AND type = Risk AND "Next review" is EMPTY |
None |
| Every risk has an owner | project = RISK AND type = Risk AND assignee is EMPTY |
None, unless you left Owner unmapped |
| The register, in order | project = RISK AND type = Risk AND statusCategory != Done ORDER BY "Risk score" DESC |
The rollback risk (R06) first, at 20 |
To keep scores right from now on, add an automation rule in Space settings > Automation: the Field value changed trigger on Risk likelihood and Risk impact, a JQL condition that both are set, and an Edit work item action that sets Risk score to:
{{#=}}{{issue.Risk likelihood.value.left(1)}} * {{issue.Risk impact.value.left(1)}}{{/}}
Moving an existing Excel register
Clean up before you import
- One risk per row, one header row. Unmerge cells, and delete subtotal rows, spacer rows and extra header rows.
- Split combined cells. A “4x3” or “H/M” column becomes separate likelihood and impact columns.
- Translate old scales once. If the old register rated risks High, Medium and Low, decide what each becomes on the 1 to 5 scales, write it down, and convert every row the same way. The importer’s Map field value step can do the translation too.
- Values, not formulas. Paste score columns as values, and remove macros and lookups to other sheets.
- Owners as email addresses, as above.
- One current state per risk. Old registers often pile dated notes into one cell. Keep the latest update in the row and leave the rest in the spreadsheet.
- Weed it. Merge duplicates, and leave out risks that can no longer happen.
What to keep in Excel
- Closed risks and old reviews. Import the open risks, plus any closed ones people still ask about. Keep the rest in a read-only archive copy.
- Rating history. Jira’s history for each risk starts at the import. Earlier scores and review notes stay in the spreadsheet.
- Reports already sent. Snapshots that went to a board or an auditor record what was reported at the time; keep them as they are.
Rate the imported risks with Risk Register for Jira
The import gives every risk a likelihood, an impact and a score. In Risk Register for Jira you rate the risks on a matrix:
- Set up probability and impact levels that match the template’s scales, with the same descriptions (probability levels, impact levels), and risk levels Low, Medium, High and Extreme, each with its own color.
- In the matrix settings, choose the level each pair of probability and impact gives.
- Open Risk Register in the space and load the imported risks with JQL such as
type = Risk(the search is already limited to the space). Risk Register keeps its ratings in its own fields, so pick each risk’s probability and impact in the grid, using the template’s likelihood and impact as your guide. Add a residual rating as each response takes effect. - The initial risk matrix then shows how many risks sit in each cell, and the residual matrix shows where treatment moved them.
Once the risks are rated in Risk Register, review them there, and keep the imported Risk likelihood, Risk impact and Risk score only as a record of the import, so the two ratings don’t drift apart.
Questions
Does the template work in Google Sheets?
Yes. Open it with File > Import in Google Sheets, and save it for Jira with File > Download > Comma Separated Values (.csv).
Why are likelihood and impact written as “3 Possible” and not just 3?
The number keeps the options in order wherever Jira sorts them by name, and lets an automation rule work out the score. The word keeps ratings consistent: people agree on what “Possible” means more readily than on what 3 means.
How many risks should a register hold?
As many as the team can review properly. If a review can’t get through the open risks, merge near duplicates, close the risks that can no longer happen, and review low risks less often.
Can we keep the register in Excel and in Jira at the same time?
Pick one as the source, because two copies drift apart quickly. If the actions live in Jira, keep the register there too, and export a filter to CSV for anyone who wants a spreadsheet.