How to build a risk register in Jira

What a risk register holds, and how to build one in Jira: a Risk work type, likelihood and impact fields, an automated score, a workflow and a dashboard.

A risk register is the list of what could go wrong on a project, with an owner, a rating and a plan for each risk. You can build one in Jira with a work type, a handful of fields and two automation flows, so your risk management sits next to the work that deals with it.

This guide covers what a register should hold, how to build it step by step with what Jira already has, where that build runs out, and what an app adds.

What a risk register holds

Each risk is one row in a spreadsheet register, and one work item in Jira. Most registers record the same things:

Field What it records Example
Title The risk in a few words Payment provider API change breaks checkout
Description What could happen, and why it matters now The provider is retiring the API version our checkout uses
Cause What would make it happen Our integration is pinned to the old version
Consequence What happens if it does Customers can’t pay by card until a fix ships
Owner One person who watches the risk and acts on it The tech lead
Category The kind of risk, for grouping and reports Vendor
Likelihood How likely it is, on a fixed scale 3 Possible, on a scale of 1 to 5
Impact How bad it would be, on a fixed scale 4 Major
Score Likelihood × impact 12
Response What you’ll do about it Reduce
Actions The work that carries out the response Upgrade to the current API version
Review date When the owner next checks the rating Two weeks from today
Status Where the risk is in its life Treating

The response is one of four:

  • Avoid: change the plan so the risk can’t happen, such as moving a launch out of the busiest season.
  • Reduce: lower the likelihood or the impact, such as adding a test that catches the API change.
  • Transfer: pass the cost to someone else, through a fixed-price contract or insurance.
  • Accept: take no action and keep watching. It suits risks that would cost more to treat than to bear.

Build the register in Jira, step by step

These steps work for any project, not only software: a common question on the Atlassian Community comes from a team that only wants to track risks and issues. The steps assume a company-managed space, where a Jira admin sets up work types and fields. In a team-managed space, a space admin does the same under Space settings > Work types, with Dropdown, Number, Date and Paragraph fields.

1. Add a Risk work type

First decide where risks live. A space of their own, with a key such as RISK, suits a register that several teams share or a risk committee reviews. A Risk work type in the delivery space suits one team tracking the risks of one project.

  1. Go to Settings > Work items > Work types and select Add work type.
  2. Name it Risk, keep it a standard work type, and add it to the work type scheme of the space that will hold the risks.

2. Create the fields

Go to Settings > Work items > Fields, select Create new field for each field below, and add the fields to the screens the Risk work type uses.

Field Type Options
Risk likelihood Select List (single choice) 1 Rare, 2 Unlikely, 3 Possible, 4 Likely, 5 Almost certain
Risk impact Select List (single choice) 1 Insignificant, 2 Minor, 3 Moderate, 4 Major, 5 Severe
Risk score Number Field None: automation fills it in
Risk category Select List (single choice) Technical, Schedule, Cost, Security, Vendor, People, Compliance, Operational
Risk response Select List (single choice) Avoid, Reduce, Transfer, Accept
Cause, Consequence Paragraph None
Response plan Paragraph None
Next review Date Picker None

Use Assignee as the owner, so Jira’s notifications and “assigned to me” views include risks. Track each action as a task linked to its risk, so the work shows on the team’s board and the risk shows what’s being done about it.

Two choices save trouble later:

  • Number the options. “3 Possible” sorts in the right order wherever Jira sorts by name, and the flow in the next step reads the number from it.
  • Don’t call a field just Impact. Jira Service Management has a field with that name, and two fields with one name are easy to mix up in JQL, filters and automation.

3. Work out the score with automation

  1. In the space, go to Space settings > Automation, select Create flow, then Create from scratch.

  2. Choose the Field value changed trigger and set it to watch Risk likelihood and Risk impact.

  3. Add a JQL condition, so the flow only runs once both ratings are in:

    "Risk likelihood" is not EMPTY AND "Risk impact" is not EMPTY
  4. Add the Edit work item action and set Risk score to:

    {{#=}}{{issue.Risk likelihood.value.left(1)}} * {{issue.Risk impact.value.left(1)}}{{/}}
  5. Name the flow in Flow details and turn it on.

.value returns the option’s name, such as “3 Possible”, and .left(1) keeps its first character. A risk rated 3 Possible and 4 Major scores 12. Risks rated before the flow existed stay blank until someone changes a rating.

This guide bands scores as Low 1 to 4, Medium 5 to 9, High 10 to 16 and Extreme 20 to 25. Use your organization’s bands if it has them.

4. Give risks a short workflow

Five statuses cover a risk’s life:

Status Status category Meaning
Identified To do Logged but not rated
Assessed In progress Rated, with an owner and a response
Treating In progress Actions under way
Monitoring In progress Actions done; the owner watches for change
Closed Done The risk can’t happen any more, or it happened and became an issue

Let every status move to every other: a risk in Monitoring that flares up should go straight back to Treating. In a team-managed space, edit the Risk work type’s workflow. In a company-managed space, create the workflow and assign it to Risk in the space’s workflow scheme.

5. Save the register as filters

The register itself is a saved filter. Select Filters in the sidebar, then View all work items, switch to JQL, and run:

project = RISK AND type = Risk AND statusCategory != Done ORDER BY "Risk score" DESC

Replace RISK with your space key. If your risks live in a delivery space, use that space’s key.

Save it as “Risk register” and add the risk fields as columns. Then save a filter for each question the team asks every week:

Filter JQL
High and extreme risks project = RISK AND type = Risk AND statusCategory != Done AND "Risk score" >= 10
Reviews due project = RISK AND type = Risk AND statusCategory != Done AND "Next review" <= now()
Not yet rated project = RISK AND type = Risk AND ("Risk likelihood" is EMPTY OR "Risk impact" is EMPTY)
No owner project = RISK AND type = Risk AND statusCategory != Done AND assignee is EMPTY

For a board, create a Kanban board from a filter of all risks (project = RISK AND type = Risk), with one column per status. On a company-managed board, Board settings > Card colors can color cards by query: red for "Risk score" >= 20, then amber for "Risk score" >= 10.

6. Build a dashboard

Create a dashboard and add these gadgets:

  • Filter Results on the Risk register filter, showing key, summary, assignee, Risk score and Next review.
  • Two Dimensional Filter Statistics on the same filter, with Risk likelihood on one axis and Risk impact on the other. It counts open risks for each pair, which is as close as Jira gets to a risk matrix. Sort by Natural: the numbered options keep the rows and columns in order.
  • Pie Chart of the register by Risk category.
  • Filter Results on the Reviews due filter.

Gadgets can’t group by a number field, so build the grid from the two select fields, not from Risk score.

7. Remind owners when a review is due

Add a second flow with the Scheduled trigger, running once a day on the Reviews due JQL, and a Comment on work item action: “Review due: check the likelihood and impact, update the plan, and set the next review date.” The assignee hears about it the way they hear about any comment.

Where native Jira falls short

That build is a working register, but it stops short of what risk reviews usually need:

  • No risk matrix. The two-dimensional gadget counts risks per pair as a plain table of numbers.
  • One rating per risk. Jira has no concept of initial and residual risk. Showing what treatment changed takes a second set of fields and a second flow.
  • No view of change. Each work item’s History tab records rating changes, but nothing shows how the register moved over a quarter, or which risks got worse.
  • Ratings anyone can change. Anyone who can edit the work item can pick any rating, and nobody is asked to agree.
  • Stale scores. Clear a rating and the score keeps its old value, because the flow’s condition stops it from running.
  • Bands by formula only. Multiplying treats a rare catastrophe (1 × 5) like a likely nuisance (5 × 1). A matrix set cell by cell can rate the rare catastrophe higher, which one formula can’t express.

Rate risks on a matrix with Risk Register for Jira

Risk Register for Jira rates the same work items, so the Risk work type carries over, and you can save a view of it as the register’s default. The app keeps its own ratings, so rate each risk once in its panel. In company-managed spaces its Initial Risk and Residual Risk fields work in JQL, so filters like the ones above can switch to them. It adds:

  • A matrix of your own. Name your probability, impact and risk levels, describe each one, and choose the level every pair gives, cell by cell. See configuring the risk matrix.
  • Initial and residual risk. The panel in each work item holds both ratings, before and after treatment (setting risk inside work items).
  • One grid for the whole register. Load risks with a quick search, JQL or a saved filter, rate them in place, add any Jira field as a column, and keep the saved views you use most, with one as the default.
  • Reports for the review meeting. Heat maps of initial and residual risk, risk change over time, and breakdowns by score or by any metric.
  • A history of ratings. Each work item’s Risk Register History lists every change to its ratings, who made it and when.

It runs on Atlassian Forge with no outside servers, so ratings stay in your Jira site. The getting started page and the user guide cover the setup.

Keep the register worth reading

  • Write risks as cause and effect. “Because our checkout is pinned to an old payment API, card payments could fail when the provider retires it” is a risk. “Payments” is a topic.
  • Rate together the first time. Rate three or four risks as a group before anyone rates alone, so a 4 means the same to everyone.
  • Review by score. Extreme risks weekly, high risks every two weeks, the rest monthly. Set Next review at every review.
  • Close risks. A register with 200 open items is a list nobody reads. Close risks that can no longer happen, and turn the ones that happened into issues.

Questions

Should risks get a Jira space of their own?

Give them one when several teams share the register or a risk committee reviews it. When one team owns the risks of one project, a Risk work type in that team’s space keeps them next to the work, and the same filters still find them.

What is the difference between a risk and an issue?

A risk might happen; an issue already has. When a risk happens, close it and log the issue it became, linked to the risk, so the register shows what came true.

Who should own a risk?

One named person who can act on it, usually whoever is closest to the cause. A team or a committee makes a poor owner: nobody treats the review date as theirs.

Can I bring an existing Excel register into Jira?

Yes, with Jira’s CSV importer. Create the fields and their options first, save the sheet as CSV with values that match the options exactly, and map each column to a field as you import.

Try Risk Register for Jira

Keep every risk in Jira. Rate each one on a risk matrix of your own, follow it from initial to residual risk, and give leadership heat maps they can read at a glance.