How to set up a RAID log in Jira, with a sample CSV

Set up a RAID log in Jira: work types and fields for risks, assumptions, issues and dependencies, JQL for each log, a dashboard, and a sample CSV to import.

A RAID log keeps a project’s Risks, Assumptions, Issues and Dependencies in one list that the team reviews every week. In Jira, the setup that holds up best is one space with four work types, the fields each type needs, a saved filter for each log and one dashboard.

This guide gives that setup ready to copy, a sample CSV of 14 items from a CRM rollout, and the steps to import it with Jira’s CSV importer.

What a RAID log covers

Letter What it records Example from a CRM rollout
R: Risks Things that might happen and would hurt the project The data migration overruns the cutover weekend
A: Assumptions Things the plan treats as true without proof yet Regional managers release each rep for two hours of training
I: Issues Problems that have already happened and need action Contractors can’t sign in through single sign-on
D: Dependencies What the project needs from another team or a supplier The ERP team delivers the customer master export

Some teams read the A as Actions and the D as Decisions. Actions work best as ordinary tasks, linked to the risk or issue they serve. Decisions can be a fifth work type that records the date and who decided, so nobody argues later about what was agreed. Everything below works the same whichever letters you use.

One work type or four

How to structure a RAID log is a common question on the Atlassian Community, and two setups work well:

  • One RAID item work type, with a RAID type field set to Risk, Assumption, Issue or Dependency.
  • Four work types, Risk, Assumption, Issue and Dependency, in one space.

Use four. Each type then gets:

  • Its own fields. Only risks need likelihood and impact. With one work type, every item shows every field, and nothing stops an assumption from getting a risk score.
  • Its own workflow. An assumption gets confirmed or disproved; a dependency gets requested, agreed and delivered. One workflow has to blur those.
  • Plain JQL. type = Dependency reads better than a clause on a custom field, and each type keeps its own icon in lists and on cards.

One work type is less to set up, and turning an assumption into a risk is a field edit rather than a move. Four types take a little more setup. In a company-managed space, a Jira admin adds them under Settings > Work items > Work types, adds them to the space’s work type scheme, and puts each type’s fields on its screens. In a team-managed space, a space admin adds them under Space settings > Work types, each with its own fields.

The fields for each type

Every type uses Summary, Description, Assignee as the owner, Due date, and Labels for the workstream. Due date holds the one date each type lives by, so one query finds everything that needs attention this week.

Work type Extra fields Due date means
Risk Risk likelihood, Risk impact, Risk score, Risk response Next review
Assumption None: the description says what’s assumed and what happens if it’s wrong Confirm by
Issue Priority Resolve by
Dependency None: the description says who delivers, and a link points to the work that waits Needed by

The risk fields:

Field Type Options
Risk likelihood Select List (single choice), or Dropdown in a team-managed space 1 Rare, 2 Unlikely, 3 Possible, 4 Likely, 5 Almost certain
Risk impact Select List (single choice), or Dropdown 1 Insignificant, 2 Minor, 3 Moderate, 4 Major, 5 Severe
Risk score Number Field, or Number Set by automation
Risk response Select List (single choice), or Dropdown Avoid, Reduce, Transfer, Accept

To fill in Risk score, add a flow (automation rule) in Space settings > Automation: the Field value changed trigger on Risk likelihood and Risk impact, a JQL condition that both are set ("Risk likelihood" is not EMPTY AND "Risk impact" is not EMPTY), and an Edit work item action that sets Risk score to:

{{#=}}{{issue.Risk likelihood.value.left(1)}} * {{issue.Risk impact.value.left(1)}}{{/}}

The number at the front of each option shows its rank wherever it appears and gives the flow something to multiply: 3 Possible and 4 Major score 12.

A workflow for each type

Work type Statuses
Risk Open, Treating, Monitoring, Closed
Assumption Open, Confirmed, Disproved
Issue Open, In progress, Resolved
Dependency Requested, Agreed, Delivered, Cancelled

Put Closed, Confirmed, Disproved, Resolved, Delivered and Cancelled in the Done status category. Then statusCategory != Done finds what’s still open, whatever the type. In a team-managed space, open each work type under Space settings > Work types and select Edit workflow. When you save, keep only that work type selected, so the change doesn’t reach the others. In a company-managed space, map a workflow to each work type in the space’s workflow scheme.

A dependency matters because something waits for it. Link the two with Jira’s built-in Blocks link type: on the dependency, link the waiting story or task as blocks. The story then shows that it is blocked by the dependency.

This search lists everything linked to one dependency, such as the work it holds up:

issue in linkedIssues("RAID-12")

And this one finds open work that has a blocker link, including blockers already delivered, so check each blocker’s status in the review:

issueLinkType = "is blocked by" AND statusCategory != Done

In that second search, use “is blocked by”, not “blocks”. The link type’s name is also Blocks, so issueLinkType = blocks matches both ends of every link. And Jira can’t, without an app, search for work linked to the results of another search, such as every open dependency at once.

JQL for each log

Save each of these as a filter, with your space key in place of RAID:

Log JQL
Risk log project = RAID AND type = Risk AND statusCategory != Done ORDER BY "Risk score" DESC
Assumptions to confirm project = RAID AND type = Assumption AND statusCategory != Done ORDER BY due ASC
Open issues project = RAID AND type = "Issue" AND statusCategory != Done ORDER BY priority DESC, due ASC
Dependencies due in two weeks project = RAID AND type = Dependency AND statusCategory != Done AND due <= "14d" ORDER BY due ASC
Overdue, any type project = RAID AND statusCategory != Done AND due < startOfDay()
No owner project = RAID AND statusCategory != Done AND assignee is EMPTY

The dependencies filter includes overdue ones too, since an overdue date is also less than 14 days away.

A dashboard for the weekly review

A two-column dashboard puts the log in the order a review works through it:

Left column Right column
Filter Results: Overdue, any type Filter Results: Dependencies due in two weeks
Filter Results: Open issues Filter Results: Risk log
Pie Chart: open items by work type Two Dimensional Filter Statistics: Risk likelihood against Risk impact, on the Risk log filter
Filter Results: Assumptions to confirm Filter Results: No owner

The pie chart needs a filter of its own: project = RAID AND statusCategory != Done. The two-dimensional gadget counts open risks for each pair of ratings; set it to sort by Natural, the field’s own option order, so the ratings run from 1 to 5. It groups by select list fields, not by number fields, so Risk score can’t be one of its axes.

Import the sample RAID log

Download raid-log-in-jira.csv. It holds 14 items from the rollout of a new CRM to 350 sales and support staff: five risks, three assumptions, three issues and three dependencies. It opens in Excel or any spreadsheet, so you can edit it before you import.

Type Summary Owner Due date Score Response
Risk Customer data migration overruns the cutover weekend Priya Nair 2025-06-27 12 Reduce
Risk Sales reps keep working in spreadsheets after go-live Marcus Lee 2025-07-04 12 Reduce
Risk Email sync fails the security review Hannah Okafor 2025-06-30 8 Reduce
Risk Only one admin knows the CRM configuration Daniel Kim 2025-07-11 8 Transfer
Risk ERP sync hits the vendor API limit Tom Becker 2025-07-18 9 Accept
Assumption The vendor sandbox stays available until go-live Tom Becker 2025-06-20
Assumption Regional managers release each rep for two hours of training Marcus Lee 2025-06-25
Assumption Customer email addresses in the old CRM are unique Priya Nair 2025-06-24
Issue Contractors cannot sign in through single sign-on Hannah Okafor 2025-06-18
Issue Training environment is missing the new deal stages Daniel Kim 2025-06-23
Issue Trial migration created 1,200 duplicate accounts Priya Nair 2025-06-27
Dependency IT security approves the single sign-on configuration Hannah Okafor 2025-06-30
Dependency ERP team delivers the customer master export Tom Becker 2025-07-07
Dependency Network team opens firewall rules for the integration server Tom Becker 2025-07-14

The file’s header row and its first item:

Work type,Summary,Description,Owner,Due date,Priority,Risk likelihood,Risk impact,Risk score,Risk response,Labels
Risk,"Customer data migration overruns the cutover weekend","The trial migration of 410,000 accounts took 31 hours against a 24-hour cutover window. If the live run is as slow, the old CRM stays offline into Monday trading.",Priya Nair,2025-06-27,,3 Possible,4 Major,12,Reduce,data-migration

Before you import

  1. Create the four work types and the risk fields, with options spelled exactly as in the file: “3 Possible”, not “3” or “Possible”.
  2. Replace each name in Owner with the person’s email address or Atlassian account ID. The importer matches people on those, not on names, and it can create accounts for people it doesn’t find. If you’d rather not, leave Owner out of the mapping and assign owners afterwards.
  3. Move the dates to fit your plan. Keep them in yyyy-MM-dd, or note the format your spreadsheet saves them in: Excel may rewrite them in your local date format.

Run the importer

You need the Make bulk changes global permission and permission to create work items in the space. Jira admins can also import from Settings > System > External System Import > CSV, which has more options.

  1. Go to Filters > Search work items, then select More actions (•••) > Import work items from CSV.
  2. Choose the file, leave Use an existing configuration file cleared, and select Next.
  3. Choose the RAID space, set the date format to yyyy-MM-dd (or the format your file uses), and select Next.
  4. Map each column to the field with the same name, except Owner, which goes to Assignee.
  5. Select Validate and fix anything it reports, then select Begin import. Save the configuration if you’ll import again.

Check the result with project = RAID AND created >= startOfDay(), which should list the 14 new work items. Then add the Blocks links for the three dependencies by hand: the file doesn’t carry links.

Rate the R in RAID with Risk Register for Jira

The setup above scores each risk with one number. Risk Register for Jira adds a risk matrix of your own to the risks in the log:

  • Rate the risks only. The app’s panel appears on every work type in the space, so agree that only Risk items get rated. Under Risk Register enable for certain ticket types in the app’s Advanced settings, choose Risk, which turns the risk history off for the other work types (enabling it for specific work types).
  • A matrix of your own. Name your probability, impact and risk levels, describe each one, and choose the level each pair gives (configuring the risk matrix).
  • Before and after. Each risk gets an initial and a residual rating (setting risk inside work items), and heat maps of both show the RAID review what the actions changed.
  • Who changed what. Each risk’s history lists every change to its ratings, who made it and when.

Keep the log alive

  • An owner and a date on everything. The No owner and Overdue filters should be empty after every review.
  • Work down the dashboard. Overdue items first, then dependencies, issues, risks and assumptions.
  • Close the loop on assumptions. A disproved assumption usually becomes a risk or an issue: create it, link it, and close the assumption.
  • Close dependencies on delivery, not on a promise of delivery.
  • When a risk happens, it becomes an issue. Close the risk, log the issue and link the two, so the log shows which risks came true.

Questions

What is the difference between an assumption and a risk?

An assumption is something the plan treats as true; a risk is something that might go wrong. An assumption you can’t confirm usually hides a risk: behind “the sandbox stays available” sits the risk that it won’t.

Should RAID items go on the team’s sprint board?

Usually not. A sprint board is for work the team does, and a risk or an assumption isn’t finished in a sprint. Keep RAID items on the dashboard, and put the actions they lead to on the board.

Can one RAID log cover several projects?

Yes. Add a label or a field for the project to every item and filter on it, or keep the four work types in each project’s space and search across them with type in (Risk, Assumption, "Issue", Dependency).

Should the RAID log have a space of its own?

Give it one when the log covers several teams or a whole program. For one team’s project, the four work types can sit in the delivery space, which keeps dependencies next to the work they block.

Try Risk Register for Jira

Keep every risk in Jira. Rate each one on a risk matrix of your own, follow it from initial to residual risk, and give leadership heat maps they can read at a glance.