Initial vs residual risk, with examples
Initial (inherent) risk, controls, residual risk and target risk in plain words, four worked examples, and how to record both ratings in Jira.
Initial risk, also called inherent risk, is how big a risk is before you count any controls. Residual risk is what’s left once the controls in place are working. The gap between the two shows what your controls are worth, and target risk is the level you want the residual risk to come down to.
This guide explains the terms in plain words, works through four examples on a 5x5 scale, and shows how to record both ratings in Jira, with what Jira has and with an app.
Initial, residual and target risk
- Initial (inherent) risk: the likelihood and impact of the risk as if nothing were done about it. No backups, no tests, no second supplier.
- Controls: anything that lowers the likelihood or the impact: a process, a check, a contract, a piece of technology.
- Residual risk: the likelihood and impact with today’s controls in place and working. ISO Guide 73, the risk vocabulary ISO has since replaced with ISO 31073, defined it as the risk remaining after risk treatment.
- Target risk: the rating you aim for, usually set by the organization’s risk appetite. If residual risk sits above target, you need more controls, or someone with the authority must accept the gap.
Controls work on one factor or both:
- Preventive controls lower the likelihood: code review, access limits, a retention bonus.
- Detective controls catch the risk early, so less harm is done: monitoring, alerts, reconciliations.
- Corrective controls limit the damage once it happens: failover, backups, a fallback process.
The examples below rate both factors from 1 to 5, multiply them into a score, and use these bands: Low 1 to 4, Medium 5 to 9, High 10 to 16, Extreme 20 to 25.
Four worked examples
A payment outage
An online store takes card payments through a single payment provider. When the provider goes down, checkout stops.
| Rating | Likelihood | Impact | Score |
|---|---|---|---|
| Initial | 4 Likely | 5 Severe | 20 Extreme |
| Residual | 4 Likely | 2 Minor | 8 Medium |
The controls in between:
- A second payment provider, with checkout failing over to it when the first stops answering (corrective).
- A synthetic checkout test every five minutes that pages the on-call engineer (detective).
- A failover drill every month, so everyone knows the switch works.
The likelihood doesn’t move: the provider fails as often as before. All of the reduction is in the impact. Controls often work this way, which is why it pays to rate the two factors separately.
A data breach through a vendor
A marketing team sends customer data to an email platform. A breach at the vendor would expose it.
| Rating | Likelihood | Impact | Score |
|---|---|---|---|
| Initial | 3 Possible | 5 Severe | 15 High |
| Residual | 2 Unlikely | 3 Moderate | 6 Medium |
The controls in between:
- Send only what the platform needs: email address and first name, no purchase history (lowers the impact).
- Review the vendor’s security before signing and every year after, using its independent audit reports (lowers the likelihood).
- Single sign-on with multi-factor authentication for every account on the vendor’s console (lowers the likelihood).
- A contract that requires prompt notice of a breach, and deletion of the data when the contract ends (lowers the impact).
A key person leaving mid-project
Only one engineer understands the billing integration, and the project has five months to run.
| Rating | Likelihood | Impact | Score |
|---|---|---|---|
| Initial | 3 Possible | 4 Major | 12 High |
| Residual | 2 Unlikely | 2 Minor | 4 Low |
The controls in between:
- A second engineer pairs on all billing work (lowers the impact).
- A runbook for the integration, tested by someone who didn’t write it (lowers the impact).
- A retention bonus paid at the end of the project (lowers the likelihood).
Both factors move, and the risk drops two bands.
A regulatory deadline
New reporting rules take effect on a fixed date, and the finance system has to produce the new report by then. Missing it brings fines and closer attention from the regulator.
| Rating | Likelihood | Impact | Score |
|---|---|---|---|
| Initial | 4 Likely | 5 Severe | 20 Extreme |
| Residual | 3 Possible | 4 Major | 12 High |
| Target | 2 Unlikely | 4 Major | 8 Medium |
The controls in place:
- An early gap analysis, so the scope is known (lowers the likelihood).
- A fallback: finance can produce the first reports by hand from a spreadsheet, at a cost (lowers the impact).
Residual risk is still High, above a target of Medium. Two planned controls are meant to close the gap: a dedicated team with the deadline as its only goal, and an early review of a sample report with the compliance team. They don’t count toward the residual rating until they’re in place. Until then, the sponsor either funds them or signs off on the gap.
Record initial and residual risk in Jira
Jira has no notion of initial and residual risk, so you give each rating its own fields. Create them under Settings > Work items > Fields > Create new field, and number the options so a rule can read them:
| Fields | Type | Options |
|---|---|---|
| Initial likelihood, Residual likelihood | Select List (single choice) | 1 Rare, 2 Unlikely, 3 Possible, 4 Likely, 5 Almost certain |
| Initial impact, Residual impact | Select List (single choice) | 1 Insignificant, 2 Minor, 3 Moderate, 4 Major, 5 Severe |
| Initial score, Residual score | Number Field | None |
| Target likelihood, Target impact (optional) | Select List (single choice) | As above |
Then add two automation rules in Space settings > Automation, one per pair. Each uses the Field value changed trigger on its two fields, a JQL condition that both are set, and an Edit work item action. The residual rule sets Residual score to:
{{#=}}{{issue.Residual likelihood.value.left(1)}} * {{issue.Residual impact.value.left(1)}}{{/}}
The initial rule is the same, with Initial in place of Residual. JQL then answers the first questions a review asks:
| Question | JQL |
|---|---|
| Which risks are still high or extreme after controls? | project = RISK AND statusCategory != Done AND "Residual score" >= 10 |
| Which risks have no residual rating yet? | project = RISK AND "Initial score" is not EMPTY AND "Residual score" is EMPTY |
| Which risks were extreme before controls? | project = RISK AND statusCategory != Done AND "Initial score" >= 20 |
The trouble with two sets of fields
-
Twice the fields. Six fields on every risk, eight with a target. Forms get long, and the residual pair is the one people skip.
-
Twice the rules. Two rules to maintain, and two scores that go stale when someone clears a rating.
-
No comparison in JQL. Atlassian’s JQL reference puts it plainly: “It’s not possible to compare two fields in JQL.” To find risks whose controls changed nothing, add a third number field, Risk reduction, set by a rule that watches all four ratings:
{{#=}}{{issue.Initial likelihood.value.left(1)}} * {{issue.Initial impact.value.left(1)}} - {{issue.Residual likelihood.value.left(1)}} * {{issue.Residual impact.value.left(1)}}{{/}}Then
"Risk reduction" <= 0lists them. -
Two grids that don’t connect. The Two Dimensional Filter Statistics gadget shows one pair of fields at a time, so before and after take two gadgets side by side, and neither shows where each risk moved.
-
The before picture gets overwritten. Someone updates the initial rating once the controls are in, and the comparison is gone. The History tab still has the old value, but only one work item at a time.
-
No movement over time. Counting how many risks went up or down a band over a quarter means reading each risk’s History.
Update: Jira’s formula fields, generally available since July 2026 on every plan, can calculate both scores and the risk reduction without rules, and their results work in JQL. They can’t read select lists yet, so the ratings would have to be Number fields from 1 to 5 instead of named options.
Follow a risk from initial to residual with Risk Register for Jira
Risk Register for Jira rates every risk twice, without fields or rules to build:
- Both ratings in one panel. The app’s panel in each work item takes initial probability and impact and residual probability and impact, and shows the level each pair gives (setting risk inside work items).
- Two heat maps. The initial and residual risk matrices count the risks in each cell, so a review sees at a glance what treatment changed.
- Change over time. The risk change over time report shows where initial or residual risk increased or decreased over a date range, grouped by week, month or quarter.
- History. Each work item’s Risk Register History lists every rating change, who made it and when, with the old and new values.
The app keeps its own ratings rather than reading Jira fields, so each risk is rated in its panel. The user guide covers rating risks inside work items.
Common mistakes with residual risk
- Counting controls in the initial rating. “We have backups, so the impact is low” describes residual risk. Initial risk assumes the backups don’t exist.
- Counting controls that don’t work. A backup nobody has restored, or a failover nobody has tested, shouldn’t lower the residual rating.
- Counting planned controls. Only controls in place today count. Planned ones explain how you’ll reach the target.
- Never re-rating. Controls decay: people leave, contracts lapse, alerts get switched off. Re-rate residual risk at every review, and after any incident that tests a control.
- Changing scales between ratings. Initial and residual must use the same scales, or the gap between them means nothing.
Questions
Is inherent risk the same as initial risk?
Yes, as this guide uses the terms: both mean the risk before you count any controls. Some teams call it gross risk, and call residual risk net risk. Some frameworks use inherent risk differently, so check your organization’s glossary.
Can residual risk be higher than initial risk?
Not if both are rated honestly, because controls only take risk away. If residual comes out higher, the initial rating was too low or the situation changed, and both need a fresh look. A control that brings a new risk of its own gets its own entry.
Who decides the target risk?
Whoever owns the risk appetite: usually the sponsor or a risk committee for a project, and the board for the company as a whole. The risk owner proposes the controls to get there.
Does a low risk need a residual rating?
If the initial rating is already low and nothing is done about it, residual equals initial. Record the same values anyway, so a filter for risks without a residual rating only lists the ones still waiting for one.