Value vs Effort matrix in Jira: find the quick wins
A value vs effort matrix sorts work into quick wins, big bets, fill-ins and money pits. How to score both axes, a worked example, and how to build it in Jira.
A value vs effort matrix plots each Jira issue by how much it’s worth and how much work it takes, then splits the chart into four boxes. The box with high value and low effort holds your quick wins. Jira has no 2x2 chart of its own.
This guide covers the four quadrants, how to score value and effort consistently, a worked example with eight items, and how to build the matrix in Jira, with saved filters and a dashboard or with an app.
The four quadrants
| Low effort | High effort | |
|---|---|---|
| High value | Quick wins | Big bets |
| Low value | Fill-ins | Money pits |
- Quick wins (high value, low effort): do these first.
- Big bets (high value, high effort): worth doing, but plan them and break them down. Don’t start several at once.
- Fill-ins (low value, low effort): pick these up when there’s spare capacity between bigger pieces of work.
- Money pits (low value, high effort): decline them, or rethink them until the effort comes down or the value goes up.
The names vary. You’ll also see major projects for big bets, thankless tasks or time sinks for money pits, and impact or benefit in place of value. The logic is the same.
Score value and effort consistently
The matrix is only as good as the two scores. A few rules keep them comparable:
- Use one scale per axis, such as 1 to 10, and write down what the ends mean. For value, 10 might be a large gain for most customers and 1 a nice-to-have nobody asked for. For effort, 1 is a few hours and 10 is months of the whole team’s time.
- Define value one way. Revenue, customer pain, strategic fit and risk all count, but agree which before scoring, or each person scores something different.
- Score effort relative to other items, not in hours. “Twice the size of the CSV export” is easier to agree on than “37 hours.”
- Set the line before you score. With 1 to 10, 6 and above is high. Decide it up front so nobody nudges an item across it.
- Let each side score its own axis. Product usually knows value best and engineering knows effort.
A worked example with eight items
A SaaS team’s backlog, scored from 1 to 10 on both axes:
| Item | Value | Effort | Quadrant |
|---|---|---|---|
| Fix the time zone bug in scheduled exports | 8 | 2 | Quick win |
| Saved filters on the reports page | 7 | 3 | Quick win |
| SAML single sign-on | 8 | 7 | Big bet |
| Usage-based billing | 9 | 9 | Big bet |
| Tooltips on the invoice form | 3 | 1 | Fill-in |
| Remember the last export format | 4 | 2 | Fill-in |
| Custom PDF themes per customer | 3 | 7 | Money pit |
| Rewrite the admin console | 4 | 9 | Money pit |
On the matrix, with 6 and above counting as high:
| Low effort (1 to 5) | High effort (6 to 10) | |
|---|---|---|
| High value (6 to 10) | Time zone bug, saved filters | SAML single sign-on, usage-based billing |
| Low value (1 to 5) | Invoice tooltips, last export format | Custom PDF themes, admin console rewrite |
The two quick wins go into the next sprint. The big bets need a plan: single sign-on could ship for one identity provider first, which is a smaller job. The fill-ins wait for a gap. The money pits get a conversation: the admin console rewrite is only worth it if it makes other work cheaper, and if so, its value score is wrong.
Many teams also want one number to sort by, such as value divided by effort. It helps within a quadrant, but don’t let it replace the quadrants. Here the invoice tooltips (3 ÷ 1 = 3.0) would outrank the saved filters (7 ÷ 3 = 2.3), because a ratio rewards tiny effort as much as big value.
Build a value vs effort matrix in Jira
Jira’s dashboards have no 2x2 chart, and no gadget plots two fields of your choice against each other, but saved filters can give you the quadrants as lists.
-
Create two number fields, Value and Effort, and add them to the work types you score.
-
Score the items. The line between high and low goes into the JQL, so use the one you agreed: here 6 and above is high.
-
Save four filters, one per quadrant:
Quick wins: project = APP AND statusCategory != Done AND "Value" >= 6 AND "Effort" < 6 ORDER BY "Value" DESC Big bets: project = APP AND statusCategory != Done AND "Value" >= 6 AND "Effort" >= 6 ORDER BY "Value" DESC Fill-ins: project = APP AND statusCategory != Done AND "Value" < 6 AND "Effort" < 6 ORDER BY "Effort" ASC Money pits: project = APP AND statusCategory != Done AND "Value" < 6 AND "Effort" >= 6 ORDER BY "Value" DESC -
Create a dashboard with a two-column layout and add a Filter results gadget for each filter: quick wins and fill-ins in the left column, big bets and money pits in the right. Show the Value and Effort columns in each gadget. That’s the matrix, as four lists.
What about the Two Dimensional Filter Statistics gadget? It can’t use number fields as an axis. If you score Value and Effort with select lists instead, such as High and Low, it shows a grid of counts: how many items sit in each quadrant, not which ones. That’s a fair health check for a backlog, but not a way to pick work.
If your Jira has the Formula field type, a formula field such as {Value} / {Effort} gives the ratio for sorting within a quadrant. And if your ideas live in Jira Product Discovery, its matrix view plots two fields against each other, such as value against effort.
Where it falls short
- Lists, not a picture. You see which quadrant an item is in, but not where in it: an item scored 6 for value and 5 for effort sits in the same list as one scored 10 and 1.
- The line lives in four places. Change the scale or the threshold and you edit four filters.
- Number fields don’t hold the scale. One takes 60 as readily as 6, and an item missing either score can slip through all four filters. A fifth filter catches those:
project = APP AND statusCategory != Done AND ("Value" is EMPTY OR "Effort" is EMPTY). - No view over time. Each work item’s History shows its Value and Effort changing, but nothing shows the quadrants as they stood at the last planning round.
Plot value against effort with Backlog Prioritization
Backlog Prioritization for Jira has a Value vs Effort method ready to use, with a score of (Business Value ÷ Effort) × 10, and draws the picture a Jira dashboard can’t:
- A real matrix. The matrix report, part of the Pro edition, plots any two metrics against each other, such as Business Value against Effort, so the quick wins stand out. You can change the metric on each axis.
- Score on one grid. Load the backlog with a basic search, JQL or a saved filter and score both metrics in place. Bulk Edit Metrics fills in a metric on many work items at once, and overwrites values already set when you tick Replace existing values.
- One scale. Each metric has values of its own, which you can edit, along with the formula. The defaults are the app’s own: Business Value is one to five stars, worth 1, 5, 8, 13 and 20, and Effort runs from Extra Small (1) to Extra Large (20). Edit both to 1 to 10 if you want the example’s line at 6.
- A score to sort by. Score is a Jira field, so a saved filter can rank work items with
Score is not EMPTY ORDER BY Score DESC. JQL searches the score, not the metrics behind it, so use the matrix report to see where each item sits. Like any ratio, use the score within a quadrant, not instead of one. - History. Each work item’s Backlog Prioritization History tab lists its 50 most recent rating and score changes made on the grid or in the work item, with who made each one, when, and the value before and after. Changes made with Bulk Edit Metrics aren’t listed.
Tips for using the matrix
- Do the quick wins, but don’t live there. A team that only takes quick wins never ships anything big.
- Break big bets down and score the pieces. A good first slice often lands in quick wins.
- Say no to money pits out loud. Close them with a reason rather than leaving them to rot in the backlog.
- Watch the fill-ins. Small jobs pile up and quietly eat a sprint.
- Redraw the matrix before each planning round, after the quick wins are done and new requests are in.
Questions
Is a value vs effort matrix the same as an impact effort matrix?
Yes, the same idea in different words. Teams also say benefit or ROI for the value axis, and complexity or cost for effort.
Should effort be in story points?
Only if every item has points from the same team. For a quick sort, a 1 to 10 relative scale is enough, and it works for items nobody has estimated yet.
Where do items on the line between two quadrants go?
Wherever your written rule puts them, such as 6 and above counts as high. Items close to the line are the ones worth a second look in the meeting.
How often should we redo the matrix?
Before each planning round, or whenever the backlog changes a lot. Quick wins get done and leave, new requests arrive and estimates firm up.